| 1. |
Project Initiation |
- consulting agreement formalisation
- review of existing lighting installation
- reviews of existing studies relevant
to lighting & the visual field
|
| 2. |
Draft Concept Plan |
- compile planning and design objectives
related to lighting
- lighting concept design
- budget estimates
- provide information to corporate into
draft report
|
| 3. |
Draft Design Guidelines |
- review existing guidelines and comment
on lighting issues
- prepare lighting guidelines
|
| 4. |
Public Consultation |
- no lighting specific involvement anticipated
|
| 5. |
Final concept plan & design guidelines
|
- comments and adjustments determined
by results of public consultation
- provide information to incorporate into
final report
|
| 6. |
Design & documentation of Stage 1
Works |
- provide information to incorporate into
final design presentation documents
- produce drawings and specification section
to be
- incorporated as a sub-contract within
the overall documentation
- technical review of electrical sub-contract
tenders received
|
| 7. |
Contract Administration of Stage 1 Works
|
- review of contractor's shop drawing
& compliance certificates for switchboards
and poles
- review of contractor's samples of poles
and luminaries before delivery to site
- review of switchboards at manufacturer's
premises before delivery to site
- site observation of contractor's works
|
| |
|
|
| |
|
|
| |
|
|